by f5developer | Dec 30, 2020 | Fiber Ring Project
Originally, the CARES Act required all work to be complete by today, December 30, 2020. Since the grant, the deadline was extended into next year. For our part, we are wrapping up slicing fiber connections this week and are done laying fiber everywhere except for one...
by f5developer | Dec 10, 2020 | Fiber Ring Project
Today we connected the Summit County Medical Examiners office on Summit in Akron to the fiber ring project and with it, the Summit County network. The medical examiners need to be on the network as they work hand-in-hand with the county coroner. Follow along the...
by Doug | Dec 9, 2020 | Fiber Ring Project
Today our CTO, Dustin Wright, is splicing fiber in the Ohio Building in Akron. Smile, Dustin… maybe he is smiling?!?! Follow along the process of the Fiber Ring Project with this Google Map where ORANGE indicates where conduit has been placed and GREEN is where...
by f5developer | Dec 8, 2020 | Fiber Ring Project
Today, we’re announcing that laying conduit for the fiber ring construction project is complete. Finishing fiber construction, placement, and splicing is ion track to finish before our December 30th deadline, but we’re in a full court press to get this...
by Doug | Nov 16, 2020 | Fiber Ring Project
Friday we conducted directional drilling at the Akron Bar Association at 57 S Broadway St. Directional drilling allows for the placement of conduit with minimal disturbance or disruption along the ground surface. Follow along the process of the Fiber Ring Project...
by f5developer | Nov 11, 2020 | Fiber Ring Project
This week we’re placing conduit in Akron. Today it’s along West Exchange between Water and Main Street. Follow along the process of the Fiber Ring Project with this Google Map where ORANGE indicates where conduit has been placed and GREEN is where fiber...