by Doug | Nov 16, 2020 | Fiber Ring Project
Friday we conducted directional drilling at the Akron Bar Association at 57 S Broadway St. Directional drilling allows for the placement of conduit with minimal disturbance or disruption along the ground surface. Follow along the process of the Fiber Ring Project...
by f5developer | Nov 11, 2020 | Fiber Ring Project
This week we’re placing conduit in Akron. Today it’s along West Exchange between Water and Main Street. Follow along the process of the Fiber Ring Project with this Google Map where ORANGE indicates where conduit has been placed and GREEN is where fiber...
by Doug | Nov 6, 2020 | Fiber Ring Project
Today we are laying conduit on the Northern edge of the fiber ring in Akron. Pictured, on right, is boring on Glenwood Avenue. Boring is a process that places conduit and fiber underground while minimizing digging. It offers significant environmental advantages over...
by f5developer | Nov 2, 2020 | Fiber Ring Project
Our crew is trenching in Akron. This short video shows us preparing to open trench on West Exchange / Towpath Trail bridge in Akron. Trenching is a process where instead of drilling underground, crews dig an open trench, lay the conduit in the hole, and then bury...
by Doug | Nov 2, 2020 | Fiber Ring Project
Today we’re installing fiber at the Community Alternative Sentencing Center. Follow along the process of the Fiber Ring Project with this Google Map where ORANGE indicates where conduit has been placed and GREEN is where fiber has been placed. VIEW...